Full Upgrade: Tar and Gravel Replaced with TPO

Project Information

  • ClientUltimate Heating
  • Category

When Ultimate Heating in Colorado needed a complete roof overhaul for their commercial facility, they called in the experts at B&L Roofing. The existing tar and gravel roof had reached the end of its lifespan, and the goal was to perform a full tear-off and upgrade to a highly reflective, energy-efficient white TPO (Thermoplastic Polyolefin) membrane.

Here is a step-by-step look at how the B&L Roofing crew tackled this massive project, transforming a heavy, aging roof into a sleek, modern commercial roofing system.

Phase 1: Material Staging and Preparation

Before a single rock of gravel was removed, the crew had to coordinate a massive delivery of materials. Properly staging insulation boards, adhesive, and heavy TPO rolls is critical for a smooth workflow on a roof of this size.

Extensive material staging on the original roof. A heavy TPO roll is temporarily elevated on adhesive pails over the abrasive gravel.

 

A long line of shrink-wrapped insulation boards is staged securely to keep materials organized and accessible as the tear-off progresses.
Fresh rolls of brilliant white TPO membrane await installation, a stark contrast to the dark, heavy materials of the old roof.

Phase 2: Tear-Off and Debris Management

The most labor-intensive part of the job is removing the heavy, stubborn tar and gravel system. The crew had to break down the aggregate layer and scrape the underlying substrate to ensure the new insulation boards would lay perfectly flat.

A crew member operates a mechanized sweeper to aggressively break up and remove the heavy top layer of original tar and gravel.
A clear view of the scraped black asphalt deck on the left compared to the undisturbed original gravel roof on the right.
Close-up edge detailing showing the clean, scraped substrate along the parapet wall, ready for new materials.

To keep the active commercial site clean, a strategic debris management system was set up. With Ultimate Heating operating below, minimizing disruption was key.

Edge brackets and metal decking installed over the perimeter, with a massive disposal dumpster staged directly below to catch tear-off debris. An Ultimate Heating service truck is parked safely below.

Phase 3: Substrate and Insulation Board Layout

With the tear-off complete in sections, the crew immediately moved to lay down the new foundation. Flat, uniform grey insulation/cover boards were installed directly over the old scraped deck to provide thermal resistance and a perfectly smooth base for the TPO membrane.

The B&L Roofing crew working in tandem, laying out pathways of cover boards and staging bonding adhesive.
A massive field of tightly fitted cover boards transforms the rough roof deck into a smooth, seamless canvas.
Meticulous corner detailing ensures the cover boards sit perfectly flush against the dark, primed parapet walls.

Phase 4: TPO Membrane Application and Adhesion

Once the boards were locked in, it was time to unroll the TPO. The crew utilized a fully adhered system, methodically applying specialized bonding adhesive to marry the tough, flexible membrane directly to the substrate beneath. The visual transformation during this phase is always the most dramatic.

Mid-project contrast: the coarse, dark tar and gravel of the past sits adjacent to the clean, reflective white TPO of the future.
A crew member oversees the alignment of the TPO membrane before applying the perfectly staged line of yellow-labeled bonding adhesive.
The first major run of white TPO laid down and cleanly welded.

Phase 5: Final Detailing and Finished Product

A commercial roof is only as good as its edges and penetrations. B&L Roofing finished the Ultimate Heating facility by installing crisp metal edge flashing, properly booting all roof vents, and meticulously heat-welding every seam to guarantee a watertight seal.

New white ribbed metal decking and edge flashing securely fastened to protect the roof perimeter.
A perfectly smooth, seamless transition where the finished TPO membrane wraps the raised parapet edge.
The final result: a brilliant, energy-efficient TPO commercial roofing system by B&L Roofing, complete with flawlessly sealed penetrations and pristine welded seams.

Job Complete. Ultimate Heating is now protected by a premium TPO roof that not only secures the building against harsh weather but also drastically reduces cooling costs thanks to its highly reflective surface.